Pengerukan Kali Mangga Besar Ditargetkan Selesai November

Mangga Besar River Mud Dredging Work Targeted to Complete in November

Mud dredging work at Mangga Besar River, Taman Sari, West Jakarta is targeted to complete in November 2019. Until today, dredging process has reached 50 percent.

This is the third week we dredge the mud and it has reached 50 percent of the work

West Jakarta Water Resources (SDA) Sub-department Head, Purwanti mentioned, her side started to dredge the mud since end of September. Her side plans to dredge the mud along 500 meters of the river and deepen its depth until one meter.

"This is the third week we dredge the mud and it has reached 50 percent of the work," she mentioned, Monday (10/21).

Mud Dredging on Jalan Belibis PHB Channel Being Accelerated

Her side deployed a long arm excavator and 8 trucks to help her side dredging and transporting the mud.

"There are 10 personnel deployed to dredge the mud. We target to finish it in the next three weeks," she asserted.

Linked News
Popular News indeks
  1. Water Channel on Jalan SPG 7 Being Improved

    access_time18-09-2026 remove_red_eye836 personNurito
  2. Jakarta Pushes to Strengthen Food Ecosystem

    access_time18-09-2026 remove_red_eye614 personAldi Geri Lumban Tobing
  3. Pramono Departs for New York to Discuss Climate and Food Crises

    access_time18-09-2026 remove_red_eye581 personDessy Suciati
  4. Operations of the MV Doulos Hope Ship Library Delayed

    access_time18-09-2026 remove_red_eye562 personAnita Karyati
  5. Sumenep Park Revitalization to Be Aligned with Gresik River Flow

    access_time18-09-2026 remove_red_eye463 personFolmer